Marian Medical Center Hospital Expansion

We provided and installed mechanical HVAC systems for this new four story plus basement in-patient tower addition, including a 2-story above-grade connector and tunnel to the existing hospital building.

Market

Healthcare

Delivery

Plan & Spec

Location

Santa Maria, CA

garnish_lmc

Overview

Lawson Mechanical was asked to provide and install mechanical HVAC systems for a new four story plus basement inpatient tower addition, including a 2-story above-grade connector and tunnel to existing the hospital building. The original completion date was set for December 2011, but a combination of owner funding delays and design changes led to a 140 day time extension, resulting in the actual completion date of May 4, 2012.

Contract Value

$18,786,254

Square Footage

236,658 SF

Completion

May 2012

General Contractor

Kitchell Contractors, Inc.

Owner

Marian Medical Center CHW

Architect

Mechanical Engineer

Syska Hennessy Group