This project was split across two distinct bidding packages. The Package A cgeneral contractor was Kimmel Construction, Inc, and this bid focused on the underground and site mechanical systems for the casino expansion, hotel, and central utility plant. Package B’s general contractor was the Howard S. Wright Construction Co., and this bid focused on on the above ground, site mechanical, and plumbing systems for the casino expansion and the hotel.
$11.5 million
248,515 SF
January 2005
Kimmel Construction, Howard S. Wright Construction
Tyme Maidu Tribe
Varond Design Group
McParlane & Associates